xtablo-source/.planning/phases
Arthur Belleville 5158eb09af
docs(04-02): complete kanban vertical slice plan — handlers, templates, test activation
- Add 04-02-SUMMARY.md with full decisions and deviation documentation
- Update STATE.md: Plans 01-02 done, add decisions, metrics, notes
- Update ROADMAP.md phase 4 progress (2/4 plans complete)
2026-05-15 09:35:03 +02:00
..
01-foundation test(01): user-approved human UAT items; close phase 2026-05-14 20:11:54 +02:00
02-authentication docs(02): phase 2 verification PASSED — AUTH-01..07 complete 2026-05-14 23:06:31 +02:00
03-tablos-crud docs(03): mark REVIEW.md status fixed after applying CR/WR fixes 2026-05-15 08:30:33 +02:00
04-tasks-kanban docs(04-02): complete kanban vertical slice plan — handlers, templates, test activation 2026-05-15 09:35:03 +02:00